Liquidated Damages Clause in Bangladesh: 9 Proven Drafting Rules for Successful Contracts

by Barrister Meheruba Mahbub | Nov 6, 2026 | Bangladesh Law, Commercial Law | 0 comments

A liquidated damages clause in Bangladesh fixes in advance the compensation payable for a breach, most often for late completion in construction, supply and EPC contracts. Under section 74 of the Contract Act 1872, courts and tribunals award reasonable compensation not exceeding the amount named, so the clause works as a ceiling and a strong guide rather than an automatic entitlement. Careful drafting decides whether it protects the employer or becomes the subject of a long dispute.

Liquidated damages clause in Bangladesh guide
Key takeaways
  • Section 74 of the Contract Act 1872 governs both liquidated damages and penalties; the distinction familiar in English law is largely collapsed.
  • The injured party is entitled to reasonable compensation not exceeding the amount stated, whether or not actual loss is precisely proved, though courts look at the nature of the loss.
  • A genuine pre-estimate of loss, clear triggers and a reasonable cap make enforcement much easier.
  • In construction and EPC contracts, LDs must work with extension of time, variation and force majeure provisions to avoid disputes.
  • Public contracts follow the Public Procurement Act 2006 and Public Procurement Rules 2025, with standard LD provisions.

What a liquidated damages clause does

Proving the exact loss caused by a breach can be hard, which is why a liquidated damages clause in Bangladesh is so useful. slow and expensive. A liquidated damages clause solves this by agreeing the compensation in advance, for example a fixed amount per day or week of delay, or a percentage of the contract price for failure to meet performance tests. A liquidated damages clause in Bangladesh therefore gives certainty to both parties: the employer knows what it can recover, and the contractor knows its maximum exposure for that breach.

LD clauses are common in construction, EPC, supply, IT implementation, shipbuilding and service contracts. Our EPC and O&M contracts practice drafts and negotiates these provisions for employers and contractors.

Section 74 of the Contract Act 1872

Every liquidated damages clause in Bangladesh is read against section 74. Section 74 provides that when a contract has been broken and a sum is named in the contract as the amount to be paid in case of breach, or the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused, to receive from the party in breach reasonable compensation not exceeding the amount so named or the penalty stipulated.

The effect is that Bangladeshi law, like Indian law from which the Act derives, does not draw a sharp line between enforceable liquidated damages and unenforceable penalties. Instead, the court awards reasonable compensation up to the agreed figure. Courts in South Asia have held that where loss is difficult to quantify and the sum is a genuine pre-estimate, the agreed amount can be awarded without detailed proof, while a sum that is plainly extravagant will be reduced. A liquidated damages clause in Bangladesh should be drafted with this approach in mind.

Practitioner note

Keep a short internal note, made at the time of contracting, explaining how the LD rate was calculated, such as lost revenue, financing costs or rental of alternative facilities. This evidence supports the clause as a genuine pre-estimate if it is later challenged.

Liquidated damages clause in Bangladesh drafting steps
From drafting to claiming liquidated damages

Drafting essentials

ElementGood practice
TriggerDefine the breach precisely, such as failure to achieve completion by the date for completion
RateBase it on a reasoned estimate of likely loss
CapSet a maximum aggregate amount, often a percentage of the contract price
ExclusivityState whether LDs are the sole remedy for that breach
InteractionLink to extension of time, suspension and termination rights
RecoveryAllow deduction from payments or call on performance security

LDs in construction and EPC contracts

Delay liquidated damages are standard in construction and EPC contracts, including FIDIC-based contracts widely used for donor-funded and private projects in Bangladesh. The contractor pays a daily or weekly amount for each period by which completion is late, up to a cap. Performance LDs may apply if a power plant, factory or system fails to meet guaranteed output or efficiency. A liquidated damages clause in Bangladesh in this context must work alongside extension of time provisions: if the employer caused the delay and the contract does not provide for extension, the employer may lose the right to claim LDs because time becomes "at large".

Our construction disputes practice regularly handles LD claims and defences in arbitration and court.

Public procurement contracts

A liquidated damages clause in Bangladesh public contracts is largely standardised. Contracts with government agencies follow the Public Procurement Act 2006 and the Public Procurement Rules 2025, which came into force on 28 September 2025. Standard tender documents include LD provisions, typically expressed as a percentage of contract value per day or week with an overall cap. Agencies deduct LDs from payments. Contractors should check the conditions carefully at tender stage, because negotiation is limited in public contracts.

Defences to an LD claim

A contractor facing a liquidated damages clause in Bangladesh may raise several defences:

  • Employer-caused delay. Delay caused by the employer, without an extension mechanism, can defeat LDs.
  • Entitlement to extension. The contractor may show it was entitled to more time due to variations, force majeure or late information.
  • Unreasonable amount. Under section 74, a tribunal may reduce an extravagant amount to reasonable compensation.
  • Waiver. Conduct suggesting the employer waived its right to LDs.
  • Procedural failures. Failure to give required notices or follow contractual procedures before deducting.

Claiming and recovering LDs

Enforcing a liquidated damages clause in Bangladesh requires discipline. Employers should follow the contract strictly: issue notices, certify the delay and calculate LDs as the clause provides. Where the contract allows, LDs can be deducted from interim payments or retention, or recovered by calling on performance security. If the contractor disputes the deduction, the matter goes to the contract's dispute resolution process, often adjudication or a dispute board followed by arbitration under the Arbitration Act 2001.

Supply and IT contracts

Outside construction, a liquidated damages clause in Bangladesh is common in supply agreements for machinery, raw materials and equipment, and in IT and software implementation contracts. In supply contracts, LDs usually apply per week of late delivery up to a percentage of the order value. In IT contracts, LDs may attach to missed milestones or service level failures, sometimes as service credits. These clauses should define acceptance tests and milestones clearly, because disputes often turn on whether a deliverable was actually complete.

Performance guarantees and LDs

For power plants, industrial facilities and process equipment, performance LDs compensate the employer if the plant fails to achieve guaranteed output, efficiency or emissions levels. The liquidated damages clause in Bangladesh for performance should specify the testing procedure, tolerances, the rate of LDs for each shortfall, minimum performance levels below which the employer may reject the plant, and the overall cap. Combining delay and performance LDs under a single aggregate cap is common.

Caps, exclusions and limitation of liability

Most contracts place LDs within a wider limitation of liability framework, including an overall cap on the contractor's liability and exclusions of indirect or consequential loss. Parties should check how these interact. If LDs are stated to be the sole remedy for delay, the employer generally cannot claim general damages for the same delay, even if its actual loss is higher. Conversely, if the clause is not exclusive, the employer may seek further damages. Clear drafting of a liquidated damages clause in Bangladesh avoids arguments about overlapping remedies.

Liquidated damages clause in Bangladesh key facts
How Bangladeshi law treats agreed damages

Termination for excessive delay

Many contracts give the employer a right to terminate when LDs reach their cap or delay exceeds a specified period. This is important because once the cap is reached, LDs no longer motivate the contractor to finish. The termination clause should explain the employer's rights to complete the work using others, recover additional costs and call on security. Linking the liquidated damages clause in Bangladesh to these termination rights gives the employer a complete toolkit for serious delay.

Arbitration and court approach

Many LD disputes are resolved by arbitration under the Arbitration Act 2001. Arbitral tribunals applying Bangladeshi law follow section 74 and generally respect a reasonable, negotiated LD clause between commercial parties, particularly where loss is hard to quantify. Courts reviewing arbitral awards intervene only on limited grounds. In court litigation, judges similarly look for reasonable compensation. Evidence of how the rate was set, the nature of the project and the parties' bargaining positions all influence the outcome of a dispute over a liquidated damages clause in Bangladesh.

Practical drafting checklist

  • Explain the basis for the LD rate in internal records before signing any liquidated damages clause in Bangladesh.
  • Define triggers, measurement and calculation clearly.
  • Include a reasonable cap and state whether LDs are the exclusive remedy.
  • Provide for extension of time for employer delay and force majeure.
  • Set out notice and deduction procedures.
  • Align LDs with termination and security provisions.

Contractor's perspective

Contractors should negotiate a liquidated damages clause in Bangladesh as carefully as employers. Key points include a realistic completion date, a fair rate, a reasonable cap, clear extension of time rights, exclusion of general damages for delay, and a requirement that the employer give notice before deducting. Contractors should keep detailed programmes and records of employer delays, variations and late information, because these documents will decide whether they are entitled to more time and relief from LDs.

Bonus clauses and incentives

Some contracts pair a liquidated damages clause in Bangladesh with an early completion bonus, rewarding the contractor for finishing ahead of schedule. Bonuses can align incentives on time-critical projects, such as factories needed for export seasons. If used, the bonus should be clearly defined and funded, and its relationship with LDs and extensions of time explained so that both sides understand how early and late completion are treated.

Frequently asked questions about liquidated damages clause in bangladesh

Are liquidated damages enforceable in Bangladesh?

Yes, under section 74 of the Contract Act 1872, as reasonable compensation not exceeding the agreed amount.

Do I need to prove actual loss?

Not necessarily in exact terms, but the court will award only reasonable compensation, and evidence of likely loss helps.

Is there a difference between LDs and penalties?

Section 74 treats both similarly; the court awards reasonable compensation up to the stated sum.

Should LDs be capped?

Yes. A cap is market practice and supports the reasonableness of the clause.

Can the employer deduct LDs from payments?

If the contract allows it and contractual procedures are followed.

What if the employer caused the delay?

LDs may not be recoverable for that delay, especially without an extension of time mechanism.

How we can help

We advise employers, contractors and suppliers on every liquidated damages clause in Bangladesh: drafting, negotiation, delay analysis, extension of time claims, LD deductions and disputes in arbitration and court. Learn more about our EPC and O&M contracts practice.

Speak to us

Negotiating or disputing liquidated damages?

We draft clauses that hold up and build strong cases when LDs are claimed or deducted.

Book a consultationEPC contracts practice

Primary sources: the Contract Act 1872, Public Procurement Act 2006 and Arbitration Act 2001 on the Laws of Bangladesh portal; public procurement documents from BPPA; standard construction contract forms from FIDIC.

This article is general information about Bangladeshi contract law as of October 2026 and is not legal advice. The enforceability of a clause depends on its wording and facts; take advice on your specific contract.

Written by

Related Posts

প্রবাসীদের আইনি সেবা নির্দেশিকা

প্রবাসীদের আইনি সেবা: বিদেশ থেকে মামলা ও সম্পত্তি সুরক্ষার 9টি প্রমাণিত উপায় 2026

প্রবাসীদের আইনি সেবা: বিদেশ থেকে জমি ও সম্পত্তি দেখাশোনা, পাওয়ার অব অ্যাটর্নি, অনলাইন নামজারি ও খাজনা…

read more

0 Comments

Submit a Comment

Your email address will not be published. Required fields are marked *